This #TimeLapseTuesday shows construction progress at El Paso ISD Coronado High School’s new fieldhouse. This video shows underground plumbing pipes, electrical conduits and footing reinforcement being set in place in preparation for the placement of concrete. Subsequently, the building’s footings and utility trenches were receiving concrete. The on-grade slab was cast followed by exterior and interior CMU (concrete masonry unit), which is a type of construction block unit, wall erection throughout the first floor of the new fieldhouse. Above ground plumbing and electrical rough-in continued simultaneously.